PROGRESS OF THE CONSTRUCTION WORKS

YEAR 2012


PROJECT TITLE

Construction of New vehicle garage at Department of Ayurveda, Navinna, Maharagama.

FLOOR AREA 2, 120.00 Sq.ft

SCOPE OF WORK Open Garage made out of steel structural members and roof included with a service

station for vehicles

CURRENT SITUATION Completed the Tender calling and Evaluation is in progress

PROJECT TITLE
 Construction of Stage II at Ayurvedic Hospital, Borella.

FLOOR AREA

SCOPE OF WORK

CURRENT SITUATION Renewal of Aggrement with the consulting firm is in progress

PROJECT TITLE
Construction of proposed ward complex at Ayurvedic Hospital, Yakkala.

FLOOR AREA 80 Perch

SCOPE OF WORK 10 Storied building, consisting of vehicle parking facility, Drug manufacturing unit,

Clinics, office, Bikshu wards, Children wards , Womens wards, Panchakarma treatments,

etc.

CURRENT SITUATION Designing of Project is in progress

PROJECT TITLE
Construction of proposed Doctors Rest Rooms, Ayurvedic Hospital, Kaithady

FLOOR AREA 580.00 Sq.ft

SCOPE OF WORK Single storied building with Varendah, Resting room and Bed room for male and Fe-male

doctors seperately

CURRENT SITUATION Completed the Tender calling and Evaluation is in progress

PROJECT TITLE
Construction of proposed Traditional Ayurvedic Hospital Complex at Mihintale

FLOOR AREA

SCOPE OF WORK ayurvedic hospital complex with all ayurvedic treatments and ward facilities with

mordern features to develop Tourisum

CURRENT SITUATION Designing of Project is in progress

PROJECT TITLE
Construction of proposed New 5 Storied Panchakarma building at Bandaranayake

Memorial Reaserch Hospital, Navinna.

FLOOR AREA

SCOPE OF WORK 5 Storied buildign with Panchakarma Treatment centre and Research labotary

CURRENT SITUATION Designing of Project is in progress

PROJECT TITLE
Construction of proposed Auditorium with Toilet block and canteen at National Institute

for Traditional Medicine

FLOOR AREA 2, 606.00 Sq.ft

SCOPE OF WORK Two storied building with an Auditotium and Canteen with Toilet block

CURRENT SITUATION Completed the Tender calling and Evaluation is in progress- For Stage I

PROJECT TITLE
Construction of proposed Auditorium at Herble Garden , Girandurukotte

FLOOR AREA 2, 606.00 Sq.ft

SCOPE OF WORK Two storied building with an Auditotium and Canteen with Toilet block

CURRENT SITUATION Completed the Tender calling and Evaluation is in progress- For Stage I

PROJECT TITLE
Construction of proposed Kitchen at Herble Garden, Pattipola

FLOOR AREA 2, 142.00 Sq.ft

SCOPE OF WORK Two storied building with Kitchen in Ground floor and Bed rooms in Upper floor

CURRENT SITUATION Completed the Tender calling and Evaluation is in progress- For Stage I